Construction progress. March 2019
Section A
● The reinforced concrete frame of the house is completed.
● Brick masonry is made from 3rd to 24th floors.
● Stair marches are fully assembled.
● Construction and installation work on the arrangement of a glass facade of 1st - 2nd floors
is executed on 95%
● Windows are fully assembled.
● Work on the arrangement of the floor screed continues on the 23rd floor, the rest are
executed.
● Works on the arrangement of insulation of the facade from 3rd to 16th floor are completed,
others are in operation.
● Work on the installation of a fence frame of balconies from 3rd to 24th floors completed by
80%.
● Works on the installation of engineering networks of HG-B completed by 95%.
● The heating pipes installation is completed by 95%.
● Drainage is completed by 98%.
● Works on applying plaster on walls are completed by 100%.
● Waterproofing of balconies is carried out on 3rd - 22nd floors.
● The work on installing apartment doors continues on 17th - 24th floors, the rest are
executed.
● Finishing work continues: the 4th floor is completed by 60%, 6th by 45%, 7th by 25%, 8th
by 60%, 9th by 20%, 10th by 55%, 11th by 45%, 13th by 15%, 14th by 30%, 15th by 35%,
16th by 25%, 24th by 10%.
● Installation of boiler equipment is completed by 100%.
● Gasification of the boiler on the site was completed by 98%.
Section B
● The frame of the section is completed.
● Brick masonry is made from 3th to 24th floors.
● Stair marches are fully assembled.
● Ventilation units are fully assembled.
● Windows are mounted from 3rg to 24th floors.
● Works on the installation of sanitary nets are in process.
● Sewer risers are mounted from 3rd to 24th floors.
● The first zone of water supply and heating risers from 3rd to 12th floor is completed by
100%. The work on the installation of the second water supply zone from 13th to 24th floor
has been started by 80%.
● Works on the installation of engineering networks of HG-B performed at 90%.
● The heating pipes are installed at 95%.
● Sewage is done by 90%.
● Work on insulation and installation of a ventilated facade in axes 11 / 2 -12 / 2 from 1st to
22nd floor is performed on 98%.
● Work on the installation of a fence frame of balconies from 3rd to 24th floors is completed
by 85%.
● Work is carried out on insulation of the facade from 3rd to 24th floors, executed 80%.
● Works on waterproofing balconies are completed by 100%.
● Gypsum plasters in the apartments and the ILO have been completed.
● Works on the installation of apartment doors are completed by 98%.
● Finishing works are performed on 5th, 6th floors on 90%, on the 7th floor - 99%, 8th.10th
floors - 85%, 9th - 70%, 11th floor - 75%, 12th floor - 85% , 13th floor - 25%, 14th floor -
85%, 15th floor - 70%, 16th floor - 65%, 17th floor - 15%, 18th - 65%, 19th floor - 40%, 20th
floor - by 5%, 21st-23rd floors - by 5%, 24th - by 15%.
● Started assembly of furniture and household appliances by 5th-6th floor completed by
30%, 7th completed by 99%, 8th-12th,14th completed by 5%.