Construction progress 27.12
Section "A"
The reinforced concrete frame of the building is completed.
The brickwork from the 3rd to the 24th is complete.
The staircase is fully mounted.
Construction and installation works on the glass facade of 1-2 floors and the frame installations are still in process.
Windows are mounted on floors 3 - 24.
Work is underway to make a floor screed, work is done on the 4th-16th and 19th - 21st floors.
Work is underway to arrange a balcony screed on floors 3 - 6.
Work is underway on the construction for facade insulation; work has been completed on floors from 3 to 22.
Work is underway on the installation of a balcony fence frame from floors 3 to 24, completed by 65%.
Work is underway on the installation of utility networks for hot and cold water, 50% completed.
The distribution of heating pipes is 75% completed.
Drainage is completed by 60%.
Works on putting the plaster on walls on 3, 22 and 23 floors, other is complete.
Works on the waterproofing of balconies are still in process, works have been performed on floors 3 - 22.
Works on the installation of apartment doors are in process on floors 4 - 8.
Renovation works are in process: on the 4th floor - 20%, 6th - 15%, 8th floor - 20%, 10th floor- 5% 11th- 12%.
Works are being carried out on installation of boiler equipment, finished on 75%
Works on gasification of the boiler-house on the ground are carried out, works complete on 70%.
Section "B"
Section frame is completed.
The brickwork is completed from the 3rd to the 24th floor.
The staircase is fully mounted.
The ventilation units are fully mounted.
Windows are installed from 3rd to 24th floor.
The installation of plumbing networks is in process.
Sewer risers are mounted from 3rd to 24th floor.
The first zone of the risers for water supply and heating from the 3rd to the 12th floor is mounted by 100%. Work on the installation of the second water supply zone from floors 13 to 24 began.
Heating is on throughout the section.Work is underway on the installation of utility networks for hot and cold water, 70% is completed.
The distribution of heating pipes is 100% completed.
Drainage is 90% completed.
Work is underway to make floor screeds on floors 4 - 24.
Work is being carried out on the screeds on the balconies, performed on 5 - 18 floors.
Works on insulation and installation of a ventilated facade in axes 11/2-12/2 are carried out from the 1st to the 22nd floor, 97% is completed.
Works on the installation of the frame of the balcony railing are carried out from the 3rd to the 24th floors, 82% is completed.
Work on the facade insulation is carried out from 3 to 24 floors, 85% is completed.
Works on the waterproofing of balconies are performed on floors 4 - 17.
Works on putting the plaster on walls are fully completed.
Works on the installation of apartment doors are carried out on floors 5 - 19.
Renovation works of apartments on 5th floor complete on 80%, 6th floor complete on 80%, 7th- on 100%, 8th -on 40%, 9th- on 15% ,10th- on 35%, 11th - on 10%, 12th - on 40%, 14th - on 35%, 15th- on 25%, 16th - on 10%, 18th- on 10%.
The installation of furniture and home appliances on the 7th floor has begun.