Standard One offers the following alternative options for purchasing apartments
Mortgage
Installments
Mortgage calculator
Installment calculator
Calculate your installment plan
Floor
Apartment
Floor space
Cost
Floor
Apartment
Floor space
Cost
123
add new apartment
Costs if you pay 100% 0 $

-15% of first installment

Prepayment
Some error
The minimum amount of prepayment for this type of apartment is 7000 $
Grace period
maximum installment period up to 01.02.2020
Promotion code
No active promocode
To get you discount, enter your promotion code
add promotion code
Monthly instalment 0 $
Apartment costs 0 $
RECEIVE YOUR ESTIMATION
Success
ORDER CONSULTATION
Some error
Success
23.11.2018
Construction progress 23.11

Construction progress 23.11

Section "A"

  • The reinforced concrete frame of the building is completed.
  • The brickwork from the 3rd to the 14th and from the 16th to the 23rd floors has been finished; on the 15th, 24th floors it is still in process.
  • The staircase is fully mounted.
  • Ventilation units are installed from 3rd to 24th floor.
  • Construction and installation works on the glass facade of 1-2 floors and the frame installations are still in process.
  • Windows are mounted on floors 3 - 14 and 16 - 23, work continues.
  • Work is underway to make a floor screed, work is done on the 4th-16th and 19th - 21st floors.
  • Work is underway to arrange a balcony screed on floors 3 - 6.
  • Work is underway on the construction for facade insulation; work has been completed on floors from 3 to 16.
  • Work is underway on the installation of a balcony fence frame from floors 3 to 24, completed by 47%.
  • Work is underway on the installation of utility networks for hot and cold water, 50% completed.
  • The distribution of heating pipes is 75% completed.
  • Drainage is completed by 50%.
  • Works on putting the plaster on walls on 16 - 24 floors are executed on 4 - 14 floors.
  • Works on the waterproofing of balconies are still in process, works have been performed on floors 3 - 22.
  • Works on the installation of apartment doors are in process on floors 4 - 8.
  • Finishing works are in process on the 4th, 6th, and 8th floors.

Section "B"

  • Section frame is completed.
  • The brickwork is completed from the 3rd to the 24th floor.
  • The staircase is fully mounted.
  • The ventilation units are fully mounted.
  • Windows are installed from 3rd to 24th floor.
  • The installation of plumbing networks is in process.
  • Sewer risers are mounted from 3rd to 24th floor.
  • The first zone of the risers for water supply and heating from the 3rd to the 12th floor is mounted by 100%. Work on the installation of the second water supply zone from floors 13 to 24 began.
  • Work is underway on the installation of utility networks for hot and cold water, 65% is completed.
  • The distribution of heating pipes is 90% completed.
  • Drainage is 90% completed.
  • Work is underway to make floor screeds on floors 4 - 20.
  • Work is being carried out on the screeds on the balconies, performed on 5 - 18 floors.
  • Works on insulation and installation of a ventilated facade in axes 11/2-12/2 are carried out from the 1st to the 22nd floor, 97% is completed.
  • Works on the installation of the frame of the balcony railing are carried out from the 3rd to the 24th floors, 65% is completed.
  • Work on the facade insulation is carried out from 3 to 24 floors, 80% is completed.
  • Works on the waterproofing of balconies are performed on floors 4 - 17.
  • Works on putting the plaster on walls on 3 and 21 - 23 floors, plaster on 4 - 20 and 22, 24 floors are carried out.
  • Works on the installation of apartment doors are carried out on floors 5 - 16.
  • Finishing works of apartments on 5 - 8, 10 - 12, 14 - 15 floors are carried out.

 PHOTOREPORT

03.10.2024
CONSTRUCTION PROGRESS OF S1 OBOLON. September 2024
03.10.2024
S1 TERMINAL CONSTRUCTION PROGRESS. SEPTEMBER 2024
13.09.2024
SEPTEMBER: SPECIAL OFFERS FROM S1 Terminal
all news
:
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date

We’re waiting for you at