CONSTRUCTION PROGRESS OF S1 TERMINAL. JULY 2021
Finally arrived that day when we are sharing the last news from our construction site. The construction of S1 Terminal is actively continuing and the following works were carried out in July:
- finished monolith on the 16th floor
- finished monolith on the 17th floor
At the same time, brickwork works are actively continuing:
- 11th floor brickwork completed
- 12th floor brickwork is done
We also want to share our plans for August:
- monolithic works on 18-20 floors
- brickwork 12-15 floors