CONSTRUCTION PROGRESS OF S1 POZNIAKY. MAY 2026
S1 Pozniaky Construction Update — May 2026
Progress in May:
Foundations for the residential tower section – 80% complete;
Waterproofing works for the residential section – 50% complete;
Installation of lightning protection within reinforced concrete pile cap structures – 90% complete;
Pile foundation works for the podium/commercial section – 30% complete.
Plans for June:
Completion of foundations for the residential tower section – 100%;
Waterproofing works for the residential section – 70%;
Completion of lightning protection installation within reinforced concrete pile cap structures – 100%;
Construction of reinforced concrete vertical structures for the basement level – 50%;
Construction of the basement floor slab – 30%;
Pile foundation works for the podium/commercial section – 70%;
Construction of foundations for the podium section – 10%.
Construction of S1 Pozniaky is progressing according to schedule!