CONSTRUCTION PROGRESS OF S1 OBOLON. FEBRUARY 2025
S1 Obolon Construction Update: February Progress and March Plans
The construction of S1 Obolon is progressing steadily, bringing us closer to completion. February was a productive month, with key milestones reached:
- Completion of vertical structures on the 12th floor – 100%
- Completion of the 12th-floor slab – 100%
- Completion of vertical structures on the 13th floor – 100%
- Completion of the 13th-floor slab – 100%
- Brickwork on the 3rd floor – 60%
In March, the team is set to achieve the following:
- Completion of vertical structures on the 14th floor – 100%
- Completion of the 14th-floor slab – 100%
- Completion of vertical structures on the 15th floor – 50%
- Completion of the 15th-floor slab – 20%
- Full completion of brickwork on the 3rd floor – 100%
Stay tuned for more updates as we continue shaping the future of urban living at S1 Obolon!