CONSTRUCTION PROGRESS OF S1 OBOLON. September 2024
Construction News S1 Obolon: what was done in September 2024 and plans for October
In September, a lot of important work was done at our S1 Obolon project.
- The flooring of the sixth floor has been fully completed;
- All vertical elements of the seventh floor have been installed;
- 80% of the seventh floor has been completed;
- 30% of vertical elements of the eighth floor have been installed;
- Brickwork on the second floor is 40% complete.
Plans for October 2024:
- To complete the ceiling of the seventh floor - 100%;
- Complete installation of vertical elements of the eighth floor - 100%;
- Complete 30% of the eighth floor slab;
- Complete 50% of the vertical elements of the eighth floor;
- Complete brickwork of the second floor - 100%;
- Complete 20% of the brickwork on the third floor.
October promises to be a very busy month, during which we plan to make significant progress in the construction. The team will be working at full capacity to fulfill the planned milestones and move closer to the completion of the project.