CONSTRUCTION PROGRESS OF S1 OBOLON. March 2024

CONSTRUCTION PROGRESS OF S1 OBOLON. March 2024

Construction News S1 Obolon: what was done in March 2024 and plans for April
We are pleased to share with you our achievements regarding the construction progress.

In the first month of spring, we made significant progress:
- The installation of vertical elements on the ground floor is 100% complete.
- Installation of the first floor slab is 100% complete.
- Installation of vertical elements on the second floor is 50% complete.
- Installation of the floor slab of the second floor is 50% complete.
- Brickwork in the basement has begun, with 15% of the work completed.

It is planned to be completed in April 2024:
- Installation of vertical elements of the second floor will be 100% complete.
- Installation of vertical elements of the third floor will be 50% complete.
- The third floor slab will be 30% complete.

Success does not come to those who wait. It comes to those who work. We are sure of this!
That's why our team works tirelessly to ensure the highest quality and adherence to the construction schedule.

09.04.2025
New Horizons for Investors in Ukraine: Standard One Launches S1 REIT
07.04.2025
Easter Discount on Apartments at S1 Obolon!
03.04.2025
CONSTRUCTION PROGRESS OF S1 TERMINAL. MARCH 2025
all news
8
9
10
11
13
14
15
16
17
18
19
20
:
5
10
15
20
25
30
35
40
45
50
55
data processing