01.12.2023
S1 TERMINAL CONSTRUCTION PROGRESS. November 2023
Updates from the S1 Terminal construction site!
What we have achieved in November:
- Overlapping of the third floor of the extension is completed.
- Vertical elements of the fourth floor of the extension are installed.
- Work has begun on translucent structures above the 11th floor.
What we plan for December:
- Completion of the fourth floor of the extension.
- Completion of all reinforced concrete works of the extension.
- Installation of translucent structures on the 12-14 floors of the A-axis.