Standard One offers the following alternative options for purchasing apartments
Mortgage
Installments
Mortgage calculator
Installment calculator
Calculate your installment plan
Floor
Apartment
Floor space
Cost
Floor
Apartment
Floor space
Cost
123
add new apartment
Costs if you pay 100% 0 $

-15% of first installment

Prepayment
Some error
The minimum amount of prepayment for this type of apartment is 7000 $
Grace period
maximum installment period up to 01.02.2020
Promotion code
No active promocode
To get you discount, enter your promotion code
add promotion code
Monthly instalment 0 $
Apartment costs 0 $
RECEIVE YOUR ESTIMATION
Success
ORDER CONSULTATION
Some error
Success
06.07.2026
CONSTRUCTION PROGRESS OF S1 OBOLON. JUNE 2026

CONSTRUCTION PROGRESS OF S1 OBOLON. JUNE 2026

In June 2026, the following works were completed at the site:

Brickwork — completed up to the 16th floor.

Balcony enclosures (3rd–15th floors, rear façade, sections A and B):

  • Bracket installation — 90%
  • Metal structure installation — 70%
  • Fiber cement panel installation — 70%

Heating system (up to the 16th floor) — completed.

Interior plastering (3rd–15th floors) — completed.

Floor screed (3rd–15th floors) — completed.

Monolithic works (3rd–16th floors) — completed.

Electrical works (1st–16th floors):

  • Cable tray installation — 100%
  • Floor-by-floor apartment power network installation — 100%
  • Power riser installation — 100%

External networks:

  • Water supply — 50%
  • Sewerage K1 — 50%
  • Sewerage K2 — 50%

Plans for July 2026

In July, construction crews will continue work in the following areas:

Balcony enclosures (3rd–15th floors, rear façade, sections A and B):

  • Bracket installation — up to 100%
  • Metal structure installation — up to 100%
  • Fiber cement panel installation — up to 100%

Heating system — radiator installation (1st–16th floors) — 40%.

Electrical works (1st–16th floors) — continuation.

Plumbing works (1st–16th floors) — installation of apartment water supply and sewerage networks — 60%.

Air conditioning (1st–16th floors) — installation of apartment freon lines — 50%.

External networks:

  • Water supply — 50%
  • Sewerage K1 — up to 100%
  • Sewerage K2 — up to 100%

Landscaping and site improvement — initial works will begin.

Construction continues on schedule. Stay tuned for updates — we publish detailed progress reports on the site every month.

06.07.2026
CONSTRUCTION PROGRESS OF S1 POZNIAKY. JUNE 2026
03.07.2026
CHANGED WORKING HOURS OF S1 SALES OFFICE
19.06.2026
Update on the Commissioning Timeline for S1 Obolon
all news
:
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date

We’re waiting for you at