CONSTRUCTION PROGRESS OF S1 TERMINAL. APRIL 2026
We’re sharing the latest construction progress for S1 Obolon for April and the plans for May 2026.
Completed in April
Construction Works
- Brickwork — 99%Balcony Enclosures (Floors 3–15)
Prospekt side:
- Bracket installation — 99%- Metal structure installation — 99%
- Fiber cement panel installation — 99%
Varus side:
- Bracket installation — 99%- Metal structure installation — 99%
- Fiber cement panel installation — 99%
Rear facade (Sections A & B, up to the 15th floor):
- Bracket installation — 80%- Metal structure installation — 50%
- Fiber cement panel installation — 50%
Engineering Systems (up to the 16th floor)
- Heating manifold installation — 80%- Water supply manifold installation — 80%
- Radiator installation — 50%
Interior Works
- Plastering (floors 11–15) — 100%- Floor screeding (floors 11–15) — 100%
Plans for May 2026
Construction Works
- Completion of brickwork up to the 16th floor- Completion of monolithic works (floors 3–16)
Balcony Enclosures (rear facade, Sections A & B, up to the 15th floor)
- Bracket installation — 90%- Metal structure installation — 70%
- Fiber cement panel installation — 70%
Engineering Systems
Completion of heating systems up to the 16th floor:
- Heating manifolds — 100%- Water supply manifolds — 100%
- Radiators — 100%
Interior Works
- Completion of plastering (floors 3–15)- Completion of floor screeding (floors 3–15)
Electrical Works (floors 1–16)
- Cable tray installation — 100%- Installation of apartment floor power networks — 80%
- Installation of power risers — 80%
External Utilities
- Water supply — 50%- Sewer system K1 — 50%
- Sewer system K2 — 50%