Standard One offers the following alternative options for purchasing apartments
Mortgage
Installments
Mortgage calculator
Installment calculator
Calculate your installment plan
Floor
Apartment
Floor space
Cost
Floor
Apartment
Floor space
Cost
123
add new apartment
Costs if you pay 100% 0 $

-15% of first installment

Prepayment
Some error
The minimum amount of prepayment for this type of apartment is 7000 $
Grace period
maximum installment period up to 01.02.2020
Promotion code
No active promocode
To get you discount, enter your promotion code
add promotion code
Monthly instalment 0 $
Apartment costs 0 $
RECEIVE YOUR ESTIMATION
Success
ORDER CONSULTATION
Some error
Success
04.05.2026
CONSTRUCTION PROGRESS OF S1 TERMINAL. APRIL 2026

CONSTRUCTION PROGRESS OF S1 TERMINAL. APRIL 2026

We’re sharing the latest construction progress for S1 Obolon for April and the plans for May 2026.

Completed in April

Construction Works

- Brickwork — 99%

Balcony Enclosures (Floors 3–15)

Prospekt side:

- Bracket installation — 99%
- Metal structure installation — 99%
- Fiber cement panel installation — 99%

Varus side:

- Bracket installation — 99%
- Metal structure installation — 99%
- Fiber cement panel installation — 99%

Rear facade (Sections A & B, up to the 15th floor):

- Bracket installation — 80%
- Metal structure installation — 50%
- Fiber cement panel installation — 50%

Engineering Systems (up to the 16th floor)

- Heating manifold installation — 80%
- Water supply manifold installation — 80%
- Radiator installation — 50%

Interior Works

- Plastering (floors 11–15) — 100%
- Floor screeding (floors 11–15) — 100%

Plans for May 2026

Construction Works

- Completion of brickwork up to the 16th floor
- Completion of monolithic works (floors 3–16)

Balcony Enclosures (rear facade, Sections A & B, up to the 15th floor)

- Bracket installation — 90%
- Metal structure installation — 70%
- Fiber cement panel installation — 70%

Engineering Systems

Completion of heating systems up to the 16th floor:

- Heating manifolds — 100%
- Water supply manifolds — 100%
- Radiators — 100%

Interior Works

- Completion of plastering (floors 3–15)
- Completion of floor screeding (floors 3–15)

Electrical Works (floors 1–16)

- Cable tray installation — 100%
- Installation of apartment floor power networks — 80%
- Installation of power risers — 80%

External Utilities

- Water supply — 50%
- Sewer system K1 — 50%
- Sewer system K2 — 50%
08.05.2026
CONSTRUCTION PROGRESS OF S1 POZNIAKY. APRIL 2026
27.04.2026
Planned Price Increase at S1 Pozniaky Starting May 15
10.04.2026
UPDATED WORKING HOURS OF THE S1 OBOLON SALES DEPARTMENT
all news
:
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date

We’re waiting for you at