13.10.2025

CONSTRUCTION PROGRESS OF S1 TERMINAL. SEPTEMBER 2025
Construction Progress of S1 Terminal: Results for September and Plans for October
The Standard One team continues active work on the S1 Terminal project. Here’s a summary of the progress made in September and the plans for the upcoming month.
Completed in September:
Ventilated faсade (4th–25th floors) — 95%
Installation of metal structures for the canopy (Sicheslavska St.) — 100%
Four-story annex near the service core — 90%
Plans for October:
Complete the ventilated faсade — 100%
Complete the annex near the service core — 100%
The construction work continues at a steady pace, maintaining the planned quality standards.