CONSTRUCTION PROGRESS OF S1 OBOLON. SEPTEMBER 2025
We’re glad to share the latest construction updates on S1 Obolon.
In September, the construction team was simultaneously working on several stages of the project — brick masonry, window installation, façade finishing, and engineering system installation.
Here’s what has been completed in more detail:
- Brick masonry of internal walls:
5th floor — 50%, 7th floor — 50%, 8th floor — 100%, 9th floor — 50%
- Window installation:
13th and 14th floors — 100%
- Wet facade (base finishing):
9th floor — 100%, 10th floor — 50%, 11th floor — 50%
- Balcony railings:
Brackets — 20%, metal structures — 20%
- Heating and water supply risers (up to 15th floor): 100%
- Interior plastering:
3rd floor — 50%, 4th floor — 100%
- Balcony screed:
3rd, 4th, and 5th floors — 100%
Plans for October:
- Complete brick masonry of internal walls on the 5th, 7th, and 9th floors (100%)
- Start masonry work on the 14th floor (50%)
- Install windows on the 15th floor (100%)
- Complete façade works up to the 12th floor and start on the 13th–14th floors
- Continue balcony installation, interior plastering, floor screed, and floor-by-floor heating system installation
Construction is progressing according to schedule, and we’ll continue to keep you updated every step of the way.