Standard One offers the following alternative options for purchasing apartments
Mortgage
Installments
Mortgage calculator
Installment calculator
Calculate your installment plan
Floor
Apartment
Floor space
Cost
Floor
Apartment
Floor space
Cost
123
add new apartment
Costs if you pay 100% 0 $

-15% of first installment

Prepayment
Some error
The minimum amount of prepayment for this type of apartment is 7000 $
Grace period
maximum installment period up to 01.02.2020
Promotion code
No active promocode
To get you discount, enter your promotion code
add promotion code
Monthly instalment 0 $
Apartment costs 0 $
RECEIVE YOUR ESTIMATION
Success
ORDER CONSULTATION
Some error
Success
02.05.2025
CONSTRUCTION PROGRESS OF S1 TERMINAL. APRIL 2025

CONSTRUCTION PROGRESS OF S1 TERMINAL. APRIL 2025

In April, 60% of the brackets, insulation, and aluminum profiles for the ventilated facade system were installed (floors 7–24, excluding the 22nd floor) at the Terminal project.

40% of aluminum window and door system production and installation has been completed.

In May, we plan to reach 80% completion of facade works, 100% installation of window and door systems, complete the construction of the water metering unit, and start building the four-story annex.

The work is progressing on schedule.

02.05.2025
CONSTRUCTION PROGRESS OF S1 OBOLON. APRIL 2025
30.04.2025
Launch of the New Investment Fund S1 Obolon by S1 REIT
29.04.2025
Update on S1 Obolon Commissioning Timeline
all news
:
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date

We’re waiting for you at