CONSTRUCTION PROGRESS OF S1 TERMINAL. MARCH 2025
Construction Progress: March Summary & April Plans
We continue sharing updates from the construction site.
March achievements:
- 40% of ventilated façade system installation completed (7–24 floors, except 22nd).
- 20% of aluminum window-door systems manufactured and installed.
- 100% of the sail metal structure assembled.
April plans:
- Completing another 60% of the ventilated façade system.
- Advancing aluminum construction installation to 40%.
The project is progressing on schedule!