CONSTRUCTION PROGRESS OF S1 OBOLON. MARCH 2025
Construction Update S1 Obolon: Achievements of March and Plans for April
We continue to actively work on the S1 Obolon project and are excited to share the results of our work for March 2025. This month, we have reached several important milestones:
14th Floor: The installation of vertical elements and the ceiling slab has been completed. This is a significant step in construction, bringing us closer to finishing this stage.
3rd Floor: The brickwork on this floor is 100% complete. This means this phase of work is successfully finished, and we can move forward.
15th Floor: 50% of the work has been completed, indicating steady progress in construction.
Plans for April 2025:
In April, we have set new ambitious goals, and here’s what’s coming up:
Completion of the installation of vertical elements and ceiling slabs on the 15th floor.
Start of work on the 16th floor.
Completion of the brickwork on the facade of the 9th, 10th, and 11th floors.
Your investment property is nearing completion! We continue to work hard to ensure its high-quality execution so that you can enjoy guaranteed results. Stay tuned for our updates and keep up with all of our achievements!