CONSTRUCTION PROGRESS OF S1 OBOLON. November 2024
Construction News S1 Obolon: what was done in November 2024 and plans for December
In November, several key stages of construction were completed at S1 Obolon:
- The vertical structures of the 9th floor were fully erected.
- The floor slab of the 9th floor is fully ready.
- The vertical structures of the 10th floor are 50% complete.
- The facade brickwork of the 5th and 6th floors has been completed.
Plans for December 2024
- Complete the construction of vertical structures on the 10th floor.
- Completion of the floor slab on the 10th floor.
- Complete 50% of the vertical structures of the 11th floor.
- Complete the floor slab of the 11th floor by 50%.
- Complete the facade brickwork of the 7th and 8th floors.
The works on the site are going according to plan so that you can get the keys to your new home as soon as possible!