Standard One offers the following alternative options for purchasing apartments
Mortgage
Installments
Mortgage calculator
Installment calculator
Calculate your installment plan
Floor
Apartment
Floor space
Cost
Floor
Apartment
Floor space
Cost
123
add new apartment
Costs if you pay 100% 0 $

-15% of first installment

Prepayment
Some error
The minimum amount of prepayment for this type of apartment is 7000 $
Grace period
maximum installment period up to 01.02.2020
Promotion code
No active promocode
To get you discount, enter your promotion code
add promotion code
Monthly instalment 0 $
Apartment costs 0 $
RECEIVE YOUR ESTIMATION
Success
ORDER CONSULTATION
Some error
Success
03.12.2024
S1 TERMINAL CONSTRUCTION PROGRESS. NOVEMBER 2024

S1 TERMINAL CONSTRUCTION PROGRESS. NOVEMBER 2024

Construction News S1 Terminal: what was done in November 2024 and plans for December


In November, several key construction stages were completed at S1 Terminal:

On the Polzunova Street side, all external works have been completed

On the Novus side:

  • The installation of aluminum profiles on the facade from the 13th to the 24th floor was completed.
  • The installation of fire protection cut-offs and tides on the same floors has been fully completed.


Plans for December 2024:

Novus side - complete the installation of fiber cement slabs on the facade from the 13th to the 24th floor.


The works on the site are progressing according to the schedule so that you can get a return on your investment as soon as possible!

19.11.2024
S1 OBOLON: SCHEDULED PRICE INCREASE FROM 1.12.2024
08.11.2024
November: SPECIAL OFFERS FROM S1 OBOLON
06.11.2024
S1 TERMINAL CONSTRUCTION PROGRESS. OCTOBER 2024
all news
:
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date

We’re waiting for you at