S1 TERMINAL CONSTRUCTION PROGRESS. OCTOBER 2024
S1 Terminal construction news: what was done in October 2024 and plans for November.
October's works were completed according to plan:
- the ventilated facade on the Sicheslavska Street side was fully completed.
On the side of Novus:
- installation of aluminum profiles of the NVF system from the level of +38.914m to +72.811m (13-24 floors) is completed
- fabrication and installation of fire protection cut-offs and tides from the ACP of the NVF system from the mark +38.914m to +72.811m (13-24 floors) - 70%
Plans for November 2024:
On the Novus side:
- fabrication and installation of fire cut-offs and tides from the ACP system of the NVF from the mark +38.914m to +72.811m (13-24 floors) - 100%
- installation of aluminum profiles and slopes from fiber cement slabs of the NVF system from the mark +38.914m to +72.811m (13-24 floors) - 100%
- cutting and installation of fiber cement slabs of the NVF system from the mark +38.914m to +72.811m (13-24 floors) - 50%