S1 TERMINAL CONSTRUCTION PROGRESS. July 2024
Construction News S1 Terminal: what we did in July 2024 and our plans for August
Despite the abnormal heat wave that lasted this month, we continued to build at the planned pace.
In July, we did the following:
- Completed the full installation of aluminum and galvanized brackets of the NVF system from the level of +38.914m to +72.839m at the level from the 13th to the 24th floors - 100%
- Installation of insulation in 2 layers, NVF system at the level from the 13th to the 24th floors has begun
Plans for August 2024:
- To complete 100% of the installation of insulation in 2 layers, NVF system from the level of +38.914m to +72.839m (13-24 floors)
- To complete the installation of aluminum profiles of the NVF system from the mark +38.914m to +72.839m (13-24 floors)