CONSTRUCTION PROGRESS OF S1 OBOLON. July 2024
Construction News S1 Obolon: what we did in July 2024 and plans for August
Despite the abnormal heat wave that lasted this month, we continued to build at the planned pace.
In July, we completed:
- Installation of vertical elements of the fifth floor - completed in full.
- Installation of the fifth floor slab - 80% complete.
- We finished the brickwork of the basement.
Plans for August 2024:
- Installation of the fifth floor slab - 100%.
- Installation of vertical elements of the sixth floor - 100%.
- Installation of the floor slab of the sixth floor - 50%.
- Brickwork on the second floor will be completed by 15%.