CONSTRUCTION PROGRESS OF S1 OBOLON. JUNE 2024
Construction News S1 Obolon: what was done in June 2024 and plans for July
Construction is moving according to plan, and we are very pleased with how things are going.
In June, it was done:
- Installation of vertical elements on the fourth floor - 100%.
- Installation of the fourth floor slab is 70% complete
- Installation of vertical elements of the fifth floor has begun
- And almost finished the brickwork of the basement - 90% of the work has been completed
Plans for July 2024:
- Installation of the fourth floor slab - 100% complete
- Installation of vertical elements of the fifth floor - 100% complete
- Installation of the floor slab of the fifth floor - 50%
- Completion of brickwork in the basement - 100% complete