Standard One offers the following alternative options for purchasing apartments
Mortgage
Installments
Mortgage calculator
Installment calculator
Calculate your installment plan
Floor
Apartment
Floor space
Cost
Floor
Apartment
Floor space
Cost
123
add new apartment
Costs if you pay 100% 0 $

-15% of first installment

Prepayment
Some error
The minimum amount of prepayment for this type of apartment is 7000 $
Grace period
maximum installment period up to 01.02.2020
Promotion code
No active promocode
To get you discount, enter your promotion code
add promotion code
Monthly instalment 0 $
Apartment costs 0 $
RECEIVE YOUR ESTIMATION
Success
ORDER CONSULTATION
Some error
Success
05.02.2024
CONSTRUCTION PROGRESS OF S1 OBOLON. JANUARY 2024

CONSTRUCTION PROGRESS OF S1 OBOLON. JANUARY 2024

Update from the construction site of S1 Obolon by Standard One!

Hello, friends! We are pleased to share with you our achievements at the S1 Obolon project in January 2024:

- The installation of vertical elements of the 0.000 elevation has reached 20%.
- Completion of the floor slab at the 0,000 mark.
- The parking lot floor slab is 80% complete.

Plans for February 2024:

- Arrangement of vertical elements of the high-rise part of the 0,000 mark to 100%.
- Installation of the ground floor slab by 50%.

19.11.2024
S1 OBOLON: SCHEDULED PRICE INCREASE FROM 1.12.2024
08.11.2024
November: SPECIAL OFFERS FROM S1 OBOLON
06.11.2024
S1 TERMINAL CONSTRUCTION PROGRESS. OCTOBER 2024
all news
:
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date

We’re waiting for you at