01.12.2023
![CONSTRUCTION PROGRESS OF S1 OBOLON. November 2023](https://s1.ua/blog/182-single-default-en/construction-progress-of-s1-obolon-november-2.jpg)
CONSTRUCTION PROGRESS OF S1 OBOLON. November 2023
Latest news from the S1 Obolon construction site
- The vertical elements of the parking lot are 70% complete.
- The vertical elements of the high-rise part are 80% complete.
- Vertical waterproofing of the high-rise part is completed!
- The parking lot floor slab is 50% complete.
- The floor slab of the high-rise part is 10% complete.
Plans for December 2023:
- Completion of the floor slab of the high-rise part by 100%.
- Vertical elements of the high-rise part of the basement will be 100% complete.
- Vertical elements of the high-rise part of the 0.000 mark - by 50%.