CONSTRUCTION PROGRESS OF S1 OBOLON. October 2023

CONSTRUCTION PROGRESS OF S1 OBOLON. October 2023

Construction progress of the S1 Obolon project in October 2023:

- The grillage of the high-rise part is already in place!
- Vertical elements of the parking lot are 70% ready.
- Vertical elements of the high-rise part are 20% complete.
- Vertical waterproofing of the high-rise part is 80% ready!

Plans for November 2023:

- Bring the vertical elements of the parking lot to 100% completion.
- The vertical elements of the high-rise part will also be 100% complete.
- Complete the vertical waterproofing of the high-rise part.
- Arrange 40% of the parking lot floor slab.
- Arrange 50% of the floor slab of the high-rise part.

11.03.2025
MARCH: SPECIAL OFFERS FROM S1 OBOLON
10.03.2025
Exclusive Offer for March 8th at S1 Obolon!
07.03.2025
Updated Working Hours of the S1 Obolon Sales Department
all news
8
9
10
11
13
14
15
16
17
18
19
20
:
5
10
15
20
25
30
35
40
45
50
55
data processing