Construction progress of the S1 Obolon project in July 2023:
- ground base reinforcement (jet piles) completed;
- completion of the fence;
- completion of the pit mark 50%;
- preparation for the grillage 10%;
- Concrete foundations for the parking lot pressure wall have been concreted;
- waterproofing of the parking lot walls started 20%.
Plans for August 2023:
- 100% completion of the pit mark;
- preparation for the grillage 100%;
- execution of the parking lot foundations;
- completion of vertical elements of the parking lot 50%;
- completion of waterproofing of the parking lot walls;
- start of work on the grillage of the high part.
- ground base reinforcement (jet piles) completed;
- completion of the fence;
- completion of the pit mark 50%;
- preparation for the grillage 10%;
- Concrete foundations for the parking lot pressure wall have been concreted;
- waterproofing of the parking lot walls started 20%.
Plans for August 2023:
- 100% completion of the pit mark;
- preparation for the grillage 100%;
- execution of the parking lot foundations;
- completion of vertical elements of the parking lot 50%;
- completion of waterproofing of the parking lot walls;
- start of work on the grillage of the high part.