Construction progress of S1 TERMINAL. NOVEMBER 2020

Construction progress of S1 TERMINAL. NOVEMBER 2020

We would like to share with you the hottest news from the construction site!

In November, the days became shorter, but work on the S1 Terminal is in full swing, because the following has been done:

- almost all preparatory work has already been completed;

- 100% completed drainage system for the removal of ground and surface waters;

- the concrete work on the buttresses has been completed to strengthen the old retaining wall;

- work has begun on the installation of brickwork in the basement and has already completed 15% of the total scope;

- preparatory work is underway on the arrangement of flights of stairs;

- We prepared all the equipment for heating concrete, which will be needed in the near future to organize our works as dynamically as possible in the winter. 

Monolithic works on the 1st floor are 100% completed and are currently underway on the 2nd floor, 25% of the scope was completed in November. Now, to level the relief of the construction site, we are backfilling the sinuses, which is 90% complete

It is very easy to keep up on the latest S1 Terminal news - subscribe to our email newsletter and follow the construction through the webcam on the website.

11.03.2025
MARCH: SPECIAL OFFERS FROM S1 OBOLON
10.03.2025
Exclusive Offer for March 8th at S1 Obolon!
07.03.2025
Updated Working Hours of the S1 Obolon Sales Department
all news
8
9
10
11
13
14
15
16
17
18
19
20
:
5
10
15
20
25
30
35
40
45
50
55
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date
data processing
Virtual PBX
Virtual PBX
Do you want a call back
at certain time?
CALL
BUTTON