Construction progress. July 2019
The facade of the house is 100% ready. Pipe routing for heatingand drainage is completed.
Work on the preparation of the local area reached the final stage. Gardening is 75% completed, and paving slab laying is 63%. Work on the installation of input groups on final stage.
Finishing works are carried out on all floors. Active work is underway in the hall of section A.
Restaurants of our partners in the process of repairs and actively preparing to launch for your future comfort.
We are also pleased to announce that at the end of July / August, the process of handing over the keys to apartments and registration of ownership will begin. In the near future, for your convenience, we will write down the main stages. Follow the news on the site.