CONSTRUCTION PROGRESS OF S1 OBOLON. JULY 2026
Construction of S1 Obolon continues on schedule. July was a busy month for utility installations and facade finishing work — and August is set to build on this momentum while adding the first steps in landscaping.
WHAT WAS COMPLETED IN JULY
Balcony enclosures (floors 3–15, rear façade, sections A and B)
— Bracket installation — 90%
— Metal structure installation — 80%
— Fiber cement panel installation — 80%
Heating system (up to floor 16)
— Radiator installation — 40%
Electrical and plumbing works (floors 1–16)
— Installation of in-apartment water supply and sewage networks — 40%
Air conditioning (floors 1–16)
— Installation of in-apartment refrigerant lines — 50%
External utility networks
— Water supply — 10%
— Sewage line K1 — 90%
— Sewage line K2 — 90%
Landscaping and site development
— Works have begun
PLANS FOR AUGUST
Balcony enclosures (floors 3–15, rear façade, sections A and B)
— Bracket installation — 100%
— Metal structure installation — 80%
— Fiber cement panel installation — 80%
Heating system (up to floor 16)
— Radiator installation — 60%
Electrical and plumbing works (floors 1–16)
— Installation of in-apartment water supply and sewage networks — 50%
Air conditioning (floors 1–16)
— Installation of in-apartment refrigerant lines — 60%
External utility networks
— Water supply — 20%
— Sewage line K1 — 100%
— Sewage line K2 — 100%
Landscaping and site development
— Paving — 30%
— Irrigation system — 20%
— Outdoor lighting — 10%
Stay tuned for updates — every month we share how S1 Obolon is progressing toward completion.