CONSTRUCTION PROGRESS OF S1 POZNIAKY. JUNE 2026
In June 2026, the following works were completed at the site:
- Foundation works for the high-rise section of the building — 100%.
- Waterproofing of the residential section of the building — 60%.
- Waterproofing of the stylobate section of the building — 10%.
- Lightning protection installation in reinforced concrete pile cap structures — 100%.
- Vertical reinforced concrete structures of the basement section of the building — 15%.
- Pile field installation under the stylobate (non-residential) section of the building — 35%.
- Foundation works for the stylobate section of the building — 10%.
Plans for July 2026
In July, construction crews will continue work in the following areas:
- Waterproofing of the residential section of the building — up to 80%.
- Vertical reinforced concrete structures of the basement section of the building — up to 60%.
- Basement floor slab installation — up to 30%.
- Pile field installation under the stylobate (non-residential) section of the building — up to 80%.
Construction continues on schedule. Stay tuned for updates — we publish detailed progress reports on the site every month.