23.11.2018
Construction progress 23.11
Section "A"
- The reinforced concrete frame of the building is completed.
- The brickwork from the 3rd to the 14th and from the 16th to the 23rd floors has been finished; on the 15th, 24th floors it is still in process.
- The staircase is fully mounted.
- Ventilation units are installed from 3rd to 24th floor.
- Construction and installation works on the glass facade of 1-2 floors and the frame installations are still in process.
- Windows are mounted on floors 3 - 14 and 16 - 23, work continues.
- Work is underway to make a floor screed, work is done on the 4th-16th and 19th - 21st floors.
- Work is underway to arrange a balcony screed on floors 3 - 6.
- Work is underway on the construction for facade insulation; work has been completed on floors from 3 to 16.
- Work is underway on the installation of a balcony fence frame from floors 3 to 24, completed by 47%.
- Work is underway on the installation of utility networks for hot and cold water, 50% completed.
- The distribution of heating pipes is 75% completed.
- Drainage is completed by 50%.
- Works on putting the plaster on walls on 16 - 24 floors are executed on 4 - 14 floors.
- Works on the waterproofing of balconies are still in process, works have been performed on floors 3 - 22.
- Works on the installation of apartment doors are in process on floors 4 - 8.
- Finishing works are in process on the 4th, 6th, and 8th floors.
Section "B"
- Section frame is completed.
- The brickwork is completed from the 3rd to the 24th floor.
- The staircase is fully mounted.
- The ventilation units are fully mounted.
- Windows are installed from 3rd to 24th floor.
- The installation of plumbing networks is in process.
- Sewer risers are mounted from 3rd to 24th floor.
- The first zone of the risers for water supply and heating from the 3rd to the 12th floor is mounted by 100%. Work on the installation of the second water supply zone from floors 13 to 24 began.
- Work is underway on the installation of utility networks for hot and cold water, 65% is completed.
- The distribution of heating pipes is 90% completed.
- Drainage is 90% completed.
- Work is underway to make floor screeds on floors 4 - 20.
- Work is being carried out on the screeds on the balconies, performed on 5 - 18 floors.
- Works on insulation and installation of a ventilated facade in axes 11/2-12/2 are carried out from the 1st to the 22nd floor, 97% is completed.
- Works on the installation of the frame of the balcony railing are carried out from the 3rd to the 24th floors, 65% is completed.
- Work on the facade insulation is carried out from 3 to 24 floors, 80% is completed.
- Works on the waterproofing of balconies are performed on floors 4 - 17.
- Works on putting the plaster on walls on 3 and 21 - 23 floors, plaster on 4 - 20 and 22, 24 floors are carried out.
- Works on the installation of apartment doors are carried out on floors 5 - 16.
- Finishing works of apartments on 5 - 8, 10 - 12, 14 - 15 floors are carried out.