CONSTRUCTION PROGRESS OF S1 TERMINAL. AUGUST 2025
Construction progress at Terminal — August 2025
In August, the Terminal project reached important milestones:
- completed installation of fiber cement façade panels on the PH side (100%);
- finished insulation, substructure installation, and cladding with “Parus” fiber cement panels (100%);
- continued construction of the four-story extension near the PH (70%).
Plans for September 2025:
- full completion of ventilated façade works from the 4th to the 25th floor (100%);
- installation of metal canopy structures on Sicheslavska Street (100%);
- completion of the four-story extension near the PH (100%).
Construction is moving forward steadily and on schedule.