CONSTRUCTION PROGRESS S1 TERMINAL. FEBRUARY 2025
Construction Progress at S1 Terminal: February Updates and March Plans
February brought significant progress at S1 Obolon:
- Facade works on the courtyard side
- Installation of brackets and substructure (4th-11th floors)
- Installation of support pipes (11th-24th floors)
- 40% completion of the sail metal structure
Plans for March include:
- Further installation of brackets, insulation, and aluminum profiles (7th-24th floors, except the 22nd) – 40% completion
- Production and installation of aluminum window and door systems (12th-24th floors) – 20% completion
- Full completion of the sail metal structure