S1 OBOLON CONSTRUCTION PROGRESS. OCTOBER 2024

S1 OBOLON CONSTRUCTION PROGRESS. OCTOBER 2024

Construction News S1 Obolon: what was done in October 2024 and plans for November
In October, several key stages of construction were completed at the S1 Obolon project:
- We completed the installation of floor slabs on the seventh and eighth floors - 100% readiness.
- The vertical elements of the eighth floor are 100% ready.
- The brickwork of the second floor is fully completed (100%).
- The facade masonry of the fourth floor has been completed and work has begun on the third floor, with 20% completed.

What are we planning for November?
- Complete the vertical elements of the ninth floor and the floor slab (100%).
- Start work on the vertical elements of the tenth floor (50%).
- Complete the facade brickwork on the fifth and sixth floors (100%).

November promises to be no less productive, and we are confidently approaching the completion of this important project!

03.04.2025
CONSTRUCTION PROGRESS OF S1 TERMINAL. MARCH 2025
02.04.2025
CONSTRUCTION PROGRESS OF S1 OBOLON. MARCH 2025
11.03.2025
MARCH: SPECIAL OFFERS FROM S1 OBOLON
all news
8
9
10
11
13
14
15
16
17
18
19
20
:
5
10
15
20
25
30
35
40
45
50
55
data processing