S1 TERMINAL CONSTRUCTION PROGRESS. AUGUST 2024
Construction News S1 Terminal: what was done during August 2024 and plans for September
What was done in August:
- Fully insulated the building from the 13th to the 24th floors
- Completed the installation of aluminum profiles on the same floors
What is planned for September:
- On the side of the Novus store: We will complete the installation of aluminum and galvanized brackets, as well as insulation from the 13th to the 24th floors
- From the side of Polzunova Street: We will continue facade insulation (by 50%) on the same floors.
- We will install aluminum profiles and fiber cement slopes
- We will install fiber cement boards, which will complete the facade finishing from the 13th to the 24th floors
The beginning of autumn promises to be no less productive! We continue to work hard to complete the construction as soon as possible.