CONSTRUCTION PROGRESS OF S1 OBOLON. May 2024
Construction News S1 Obolon: what was done in May 2024 and plans for June
We are moving according to the construction plan and in May we made a lot of progress:
- Installation of vertical elements of the third floor - 100% completed
- Installation of the third floor slab - 100% completed
- Installation of vertical elements of the fourth floor - 30% completed
Plans for June 2024:
- Installation of vertical elements of the fourth floor is 100% complete
- Installation of the fourth floor slab is 100% complete
- Installation of vertical elements of the fifth floor is planned to be 30% complete
Success is achieved through action! Our team is constantly working to ensure high quality and timely completion of construction.