S1 TERMINAL CONSTRUCTION PROGRESS. FEBRUARY 2024

S1 TERMINAL CONSTRUCTION PROGRESS. FEBRUARY 2024

February, surprisingly, was kind to all of us, so the construction went according to plan. We have completed important stages, namely:

- Installation of non-ventilated facades (NVF) on floors 5-11, axis A (Vokzal side) - 100% completed

- Installation of translucent structures on floors 17-24, axis A (Novus side) and along Sicheslavska Street - also successfully completed by 100%

- Installation of the NWF side on Sicheslavska Street - 6 floors

Our team is working tirelessly to ensure the highest quality and adherence to the construction schedule!

What we are planning for March 2024:

- We will focus on the installation of the NVF on the Novus store side to ensure maximum stability and safety of the future building.

Follow our news, because the foundation on which your trust is built is transparent and detailed information about the construction progress.

09.04.2025
New Horizons for Investors in Ukraine: Standard One Launches S1 REIT
07.04.2025
Easter Discount on Apartments at S1 Obolon!
03.04.2025
CONSTRUCTION PROGRESS OF S1 TERMINAL. MARCH 2025
all news
8
9
10
11
13
14
15
16
17
18
19
20
:
5
10
15
20
25
30
35
40
45
50
55
data processing