CONSTRUCTION PROGRESS OF S1 OBOLON. FEBRUARY 2024
We are pleased to share with you the progress of the construction. In February 2024, we made significant progress:
- Installation of vertical elements of the first floor has reached 70%
- Installation of the ground floor slab is 50% complete
Our plans for March 2024:
- Installation of vertical elements of the first floor will be 100% complete
- Installation of the ground floor slab will also be 100% complete
- The installation of vertical elements of the second floor will begin, and we plan to complete this work by 50%.
- The installation of the second floor slab will also begin, with a planned volume of 50%
Success does not come to those who wait. It comes to those who work. We are sure of this!
That's why our team works tirelessly to ensure the highest quality and adherence to the construction schedule.