CONSTRUCTION PROGRESS OF S1 OBOLON. DECEMBER 2023
Update from the S1 Obolon construction site
Hello, friends! Here is the latest news on the construction progress of our S1 Obolon project for December 2023:
- The installation of the floor slab at the 0.000 mark of the high-rise part has reached 80%.
- The vertical elements of the high-rise part of the basement are already fully ready!
- Vertical elements of the high-rise part of the 0.000 mark - by 50%.
- The waterproofing of the underground part has been successfully completed.
Plans for January 2024:
- Arrangement of vertical elements of the height part of the 0,000 mark up to 100%.
- Completion of the floor slab at the 0,000 mark.
- Installation of the ground floor slab at 30%.