CONSTRUCTION PROGRESS OF S1 TERMINAL. April 2023
Spring gives us warmth, and we have started work on the construction of the S1 Terminal apart-hotel with new energy.
In April, we resumed construction work and began installing window systems (frames without glazing) along the E axis up to the eleventh floor.
In May, we plan to:
- Completion of installation of the window system (frames without glazing) along the E axis up to the eleventh floor.
- Beginning of installation of the window system (frames without glazing) up to the 11th floor along axis A and axis 15.