CONSTRUCTION PROGRESS OF S1 TERMINAL. September - October 2022
The war forever changed the lives of each of us, but it will not stop us, because we are Ukrainians. As long as the Armed Forces heroically defend the independence of our country, we must do everything possible to support the economy.
We are aware of our responsibility to our investors, and we are incredibly grateful to each of them for their trust. Since mid-September, we have resumed work at the S1 Terminal construction site and continue construction despite the obstacles.
During this time, our team:
- Completed the monolithic works of the main building to 100%.
- Arranged grills of the annex.
- Began to carry out work on modernization of networks B1, K1, K2.
We are aware of our responsibility to our investors, and we are incredibly grateful to each of them for their trust. Since mid-September, we have resumed work at the S1 Terminal construction site and continue construction despite the obstacles.
During this time, our team:
- Completed the monolithic works of the main building to 100%.
- Arranged grills of the annex.
- Began to carry out work on modernization of networks B1, K1, K2.