Construction progress of S1 TERMINAL. DECEMBER 2021
The results of our team work at 2021 on the construction site of S1 Terminal apart-hotel is clearly visible from afar. What we did in December:
- Completed monolithic works on the 25th floor and 20% of the monolith on the 26th floor
- Installed monolithic belts on the 22nd floor
- Completed 181 m2 of concrete preparation for paving the yard
- Installed an exhibitor of facade systems on the 5th floor
In January, we are planning to complete the monolith of 26th floor and arrange the pile field of the annex.