Construction progress of S1 TERMINAL. September 2021
The first month of autumn has passed quickly, and that means it's time to find out news from the construction site.
For September, the following was completed:
- finished monolith of the 20th floor
- completed monolith on the 21st floor
- finished monolith of the 22nd floor
At this moment, the monolith of the 23rd floor is in operation, 50% have already been completed. Work on the installation of brickwork continues, completed in September:
- 15th floor brickwork
- 16th floor brickwork
Works continues on the implementation of monolithic belts:
- executed on floors 12-14
For October in plans:
- monolithic works on floors 23-25
- brickwork 17-18 floors.
Stay up to date with the latest news from the construction site, subscribe to our email newsletter, or follow our construction through the webcam on website.