Standard One offers the following alternative options for purchasing apartments
Mortgage
Installments
Mortgage calculator
Installment calculator
Calculate your installment plan
Floor
Apartment
Floor space
Cost
Floor
Apartment
Floor space
Cost
123
add new apartment
Costs if you pay 100% 0 $

-15% of first installment

Prepayment
Some error
The minimum amount of prepayment for this type of apartment is 7000 $
Grace period
maximum installment period up to 01.02.2020
Promotion code
No active promocode
To get you discount, enter your promotion code
add promotion code
Monthly instalment 0 $
Apartment costs 0 $
RECEIVE YOUR ESTIMATION
Success
ORDER CONSULTATION
Some error
Success
05.07.2021
Construction progress of S1 TERMINAL. JUNE 2021

Construction progress of S1 TERMINAL. JUNE 2021

June passed very quickly, and our team is actively continuing construction of S1 Terminal in spite of rain or hot weather. During this month was completed:

- monolithic works on the 14th floor

- monolithic works on the 15th floor

Brickwork is being actively carried out on the construction of internal walls, this month completed:

- 8th floor brickwork

- 9th floor brickwork

- 10th floor brickwork

The following works are planned for July:

- monolithic works of 16-18 floors

- brickwork on 11-14 floors

We do not recommend missing the latest news from the construction site, subscribe to the email newsletter, and also follow the construction through the webcam on our website.

19.11.2024
S1 OBOLON: SCHEDULED PRICE INCREASE FROM 1.12.2024
08.11.2024
November: SPECIAL OFFERS FROM S1 OBOLON
06.11.2024
S1 TERMINAL CONSTRUCTION PROGRESS. OCTOBER 2024
all news
:
Visit our showroom.
We accurately recreate one of our future apartments.
You have the opportunity to rate the quality of renovation and furniture by our own.

“You can schedule for a preview and we will make a delicious coffee”

Incorrect name
illicit phone
incorrect mail
Please choose a different date

We’re waiting for you at