Construction progress of S1 TERMINAL. JUNE 2021
June passed very quickly, and our team is actively continuing construction of S1 Terminal in spite of rain or hot weather. During this month was completed:
- monolithic works on the 14th floor
- monolithic works on the 15th floor
Brickwork is being actively carried out on the construction of internal walls, this month completed:
- 8th floor brickwork
- 9th floor brickwork
- 10th floor brickwork
The following works are planned for July:
- monolithic works of 16-18 floors
- brickwork on 11-14 floors