Construction progress of S1 TERMINAL. APRIL 2021
For the last few months, our S1 Terminal has grown a lot, which is a happiness for us. We are glad to announce that for the month of April we exceeded the plan.
Now we are building a monolith, during this month it was completed:
- monolith of the 9th floor
- monolith of the 10th floor
- monolith of the 11th floor
Also, work continues on the brickwork installation:
- brickwork on the 2nd floor is 70% completed
- completed brickwork the 3rd floor
- completed brickwork of the 4th floor
- completed brickwork of the 5th floor
For May we have planned:
- construction of a monolith of 12-14 floors.
- brickwork 6-8 floors.
To keep in touch with the latest news from the construction site, subscribe to the email newsletter, and also follow the construction through the webcam on our website.