Construction progress of S1 TERMINAL. December 2020
So 2020 has come to an end. We are completing this year and are summarizing the work on the construction site in December:
- completed preparatory works: horizontal waterproofing of the grillage, vertical waterproofing, concrete preparation of the protective layer of waterproofing, grillage, drainage system.
- monolithic works on the 2nd floor are 100% completed.
At the moment, monolithic work is underway on the 3rd floor - 60% readiness, and the 4th - 20% readiness.
Work has begun on the construction of external networks - sewerage and water supply. This is a long period of work, but we plan to complete it as soon as possible. Also, the brickwork of the basement is underway and 80% has already been completed.
We have big plans for 2021. Therefore, follow the construction - through the webcam on our website, or subscribe to the email newsletter to stay up to date with the latest news.