Standard One предлагает следующие альтернативные варианты приобретения квартир
Ипотека
Рассрочка
Кредитный калькулятор
Калькулятор рассрочки
Поверх
Квартира
Площа
Вартість
Поверх
Квартира
Площа
Вартість
123
додати квартиру
Вартість при оплаті 100% 0 $

Только в мае 0$

Аванс
Some error
мінімальний аванс для цього типу квартир - 7000 $
Строк відтермінування
максимальный период рассрочки до 1.02.2020
Промокод
No active promocode
для отримання знижки вкажіть промокод
додати промокод
Щомісячний платіж 0 $
Загальна вартість 0 $
Отримати розрахунок
Success
Замовити консультацію
Some error
Success
27.12.2018
Construction progress 27.12

Construction progress 27.12

Section "A"

  • The reinforced concrete frame of the building is completed.

  • The brickwork from the 3rd to the 24th is complete.

  • The staircase is fully mounted.

  • Construction and installation works on the glass facade of 1-2 floors and the frame installations are still in process.

  • Windows are mounted on floors 3 - 24.

  • Work is underway to make a floor screed, work is done on the 4th-16th and 19th - 21st floors.

  • Work is underway to arrange a balcony screed on floors 3 - 6.

  • Work is underway on the construction for facade insulation; work has been completed on floors from 3 to 22.

  • Work is underway on the installation of a balcony fence frame from floors 3 to 24, completed by 65%.

  • Work is underway on the installation of utility networks for hot and cold water, 50% completed.

  • The distribution of heating pipes is 75% completed.

  • Drainage is completed by 60%.

  • Works on putting the plaster on walls on 3, 22 and 23 floors, other is complete.

  • Works on the waterproofing of balconies are still in process, works have been performed on floors 3 - 22.

  • Works on the installation of apartment doors are in process on floors 4 - 8.

  • Renovation works are in process: on the 4th floor - 20%, 6th - 15%, 8th floor - 20%, 10th floor- 5% 11th- 12%.

  • Works are being carried out on installation of boiler equipment, finished on 75%

  • Works on gasification of the boiler-house on the ground are carried out, works complete on 70%.



Section "B"

  • Section frame is completed.

  • The brickwork is completed from the 3rd to the 24th floor.

  • The staircase is fully mounted.

  • The ventilation units are fully mounted.

  • Windows are installed from 3rd to 24th floor.

  • The installation of plumbing networks is in process.

  • Sewer risers are mounted from 3rd to 24th floor.

  • The first zone of the risers for water supply and heating from the 3rd to the 12th floor is mounted by 100%. Work on the installation of the second water supply zone from floors 13 to 24 began.
    Heating is on throughout the section.

  • Work is underway on the installation of utility networks for hot and cold water, 70% is completed.

  • The distribution of heating pipes is 100% completed.

  • Drainage is 90% completed.

  • Work is underway to make floor screeds on floors 4 - 24.

  • Work is being carried out on the screeds on the balconies, performed on 5 - 18 floors.

  • Works on insulation and installation of a ventilated facade in axes 11/2-12/2 are carried out from the 1st to the 22nd floor, 97% is completed.

  • Works on the installation of the frame of the balcony railing are carried out from the 3rd to the 24th floors, 82% is completed.

  • Work on the facade insulation is carried out from 3 to 24 floors, 85% is completed.

  • Works on the waterproofing of balconies are performed on floors 4 - 17.

  • Works on putting the plaster on walls are fully completed.

  • Works on the installation of apartment doors are carried out on floors 5 - 19.

  • Renovation works of apartments on 5th floor complete on 80%, 6th floor complete on 80%, 7th- on 100%, 8th -on 40%, 9th- on 15% ,10th- on 35%, 11th - on 10%, 12th - on 40%, 14th - on 35%, 15th- on 25%, 16th - on 10%, 18th- on 10%.

  • The installation of furniture and home appliances on the 7th floor has begun.

   PHOTOREPORT

29.09.2020
Special offer!
14.09.2020
Investment in an apart-hotel
28.08.2020
CONSTRUCTION PROGRESS S1 TERMINAL. AUGUST 2020
כל החדשות
Get the presentation about Standard One Terminal by mail

Get the presentation about Standard One Terminal by mail

:
Посетите наш шоурум
Мы с точностью сделали одну из наших будущих квартир
У вас есть возможность оценить качество ремонта и мебели собственными глазами

Запишитесь на просмотр нашей квартиры, а мы угостим вас вкусным кофе

Некорректное имя
Некорректный телефон
Некорректная почта
выберите другу дату, пожалуйста

Ждем вас на чашечку кофе в