Standard One предлагает следующие альтернативные варианты приобретения квартир
Ипотека
Рассрочка
Кредитный калькулятор
Калькулятор рассрочки
Поверх
Квартира
Площа
Вартість
Поверх
Квартира
Площа
Вартість
123
додати квартиру
Вартість при оплаті 100% 0 $

Только в мае 0$

Аванс
Some error
мінімальний аванс для цього типу квартир - 7000 $
Строк відтермінування
максимальный период рассрочки до 1.02.2020
Промокод
No active promocode
для отримання знижки вкажіть промокод
додати промокод
Щомісячний платіж 0 $
Загальна вартість 0 $
Отримати розрахунок
Success
Замовити консультацію
Some error
Success
23.11.2018
Construction progress 23.11

Construction progress 23.11

Section "A"

  • The reinforced concrete frame of the building is completed.
  • The brickwork from the 3rd to the 14th and from the 16th to the 23rd floors has been finished; on the 15th, 24th floors it is still in process.
  • The staircase is fully mounted.
  • Ventilation units are installed from 3rd to 24th floor.
  • Construction and installation works on the glass facade of 1-2 floors and the frame installations are still in process.
  • Windows are mounted on floors 3 - 14 and 16 - 23, work continues.
  • Work is underway to make a floor screed, work is done on the 4th-16th and 19th - 21st floors.
  • Work is underway to arrange a balcony screed on floors 3 - 6.
  • Work is underway on the construction for facade insulation; work has been completed on floors from 3 to 16.
  • Work is underway on the installation of a balcony fence frame from floors 3 to 24, completed by 47%.
  • Work is underway on the installation of utility networks for hot and cold water, 50% completed.
  • The distribution of heating pipes is 75% completed.
  • Drainage is completed by 50%.
  • Works on putting the plaster on walls on 16 - 24 floors are executed on 4 - 14 floors.
  • Works on the waterproofing of balconies are still in process, works have been performed on floors 3 - 22.
  • Works on the installation of apartment doors are in process on floors 4 - 8.
  • Finishing works are in process on the 4th, 6th, and 8th floors.

Section "B"

  • Section frame is completed.
  • The brickwork is completed from the 3rd to the 24th floor.
  • The staircase is fully mounted.
  • The ventilation units are fully mounted.
  • Windows are installed from 3rd to 24th floor.
  • The installation of plumbing networks is in process.
  • Sewer risers are mounted from 3rd to 24th floor.
  • The first zone of the risers for water supply and heating from the 3rd to the 12th floor is mounted by 100%. Work on the installation of the second water supply zone from floors 13 to 24 began.
  • Work is underway on the installation of utility networks for hot and cold water, 65% is completed.
  • The distribution of heating pipes is 90% completed.
  • Drainage is 90% completed.
  • Work is underway to make floor screeds on floors 4 - 20.
  • Work is being carried out on the screeds on the balconies, performed on 5 - 18 floors.
  • Works on insulation and installation of a ventilated facade in axes 11/2-12/2 are carried out from the 1st to the 22nd floor, 97% is completed.
  • Works on the installation of the frame of the balcony railing are carried out from the 3rd to the 24th floors, 65% is completed.
  • Work on the facade insulation is carried out from 3 to 24 floors, 80% is completed.
  • Works on the waterproofing of balconies are performed on floors 4 - 17.
  • Works on putting the plaster on walls on 3 and 21 - 23 floors, plaster on 4 - 20 and 22, 24 floors are carried out.
  • Works on the installation of apartment doors are carried out on floors 5 - 16.
  • Finishing works of apartments on 5 - 8, 10 - 12, 14 - 15 floors are carried out.

 PHOTOREPORT

14.09.2020
Investment in an apart-hotel
28.08.2020
CONSTRUCTION PROGRESS S1 TERMINAL. AUGUST 2020
10.08.2020
A new format of real estate in Ukraine
כל החדשות
Get the presentation about Standard One Terminal by mail

Get the presentation about Standard One Terminal by mail

:
Посетите наш шоурум
Мы с точностью сделали одну из наших будущих квартир
У вас есть возможность оценить качество ремонта и мебели собственными глазами

Запишитесь на просмотр нашей квартиры, а мы угостим вас вкусным кофе

Некорректное имя
Некорректный телефон
Некорректная почта
выберите другу дату, пожалуйста

Ждем вас на чашечку кофе в